RENCANA ANGGARAN BIAYA (RAB) | |||||||||
DESA PASIR BERDENGUNG KECAMATAN PASIR LAUT | |||||||||
TAHUN ANGGARAN 2020 | |||||||||
Bidang | : | Pelaksanaan Pembangunan Desa (2) | |||||||
Sub Bidang | : | Pekerjaan Umum dan Penataan Ruang (2.3.) | |||||||
Kegiatan | : | Pembangunan Prasarana Jalan Desa (Box Culvert) (2.3.14.) | |||||||
Box Culvert RT. 1 RW. 2 Dusun Bahagia ukuran 4 m x 1,5 m x 1 m | |||||||||
Waktu Pelaksanaan | : | 10 (sepuluh hari kalender) | |||||||
Rincian Pendanaan | : | ||||||||
NO. | U R A I A N | VOLUME | HARGA SATUAN (Rp) | JUMLAH (Rp) | |||||
1 | 2 | 3 | 4 | 5 | |||||
I. | BAHAN | (Harga hanya contoh) | |||||||
1. | Semen (1 zak=50 kg) | 42.00 | zak | 90,000.00 | 3,780,000.00 | ||||
2. | Pasir Beton | 3.00 | M3 | 150,000.00 | 450,000.00 | ||||
3. | Pasir Urug | 1.00 | M3 | 140,000.00 | 140,000.00 | ||||
4. | Batu Pecah 2/3 cm | 5.00 | M3 | 500,000.00 | 2,500,000.00 | ||||
5. | Besi beton polos Ø10mm-12m | 15.00 | Btg | 100,000.00 | 1,500,000.00 | ||||
6. | Besi beton polos Ø15mm-12m | 29.00 | Btg | 200,000.00 | 5,800,000.00 | ||||
7. | Kawat Beton (Bendrat) | 8.00 | Kg | 20,000.00 | 160,000.00 | ||||
8. | Papan Mal uk. 2/18 cm- 4m | 42.00 | Kpg | 15,000.00 | 630,000.00 | ||||
9. | Kayu cerucuk Ø10cm - 4m | 65.00 | Btg | 11,000.00 | 715,000.00 | ||||
10. | Kayu 4/6 - 4m | 10.00 | Btg | 100,000.00 | 1,000,000.00 | ||||
11. | Paku Campur | 8.00 | Kg | 25,000.00 | 200,000.00 | ||||
Jumlah Bahan | 16,875,000.00 | ||||||||
II. | SEWA ALAT | ||||||||
1. | Gerobak Dorong | 2.00 | Bh | 200,000.00 | 400,000.00 | ||||
2. | Concrete mixer & operasional | 4.00 | hari | 300,000.00 | 1,200,000.00 | ||||
Jumlah Alat | 1,600,000.00 | ||||||||
III. | UPAH | ||||||||
1. | Pekerja | 35.00 | HOK | 85,000.00 | 2,975,000.00 | ||||
2. | Tukang | 13.00 | HOK | 120,000.00 | 1,560,000.00 | ||||
3. | Kepala Tukang | 2.00 | HOK | 140,000.00 | 280,000.00 | ||||
4. | Mandor | 15.00 | HOK | 120,000.00 | 1,800,000.00 | ||||
65.00 | HOK | Jumlah Upah | 6,615,000.00 | ||||||
IV. | HONOR TPK | ||||||||
1. | Ketua | 1.00 | org | 300,000.00 | 300,000.00 | ||||
2. | Sekretaris | 1.00 | org | 250,000.00 | 250,000.00 | ||||
3. | Anggota | 2.00 | org | 200,000.00 | 400,000.00 | ||||
(Perbup Sanggau No. 1 Thn. 2019) | |||||||||
4.00 | org | Jumlah Honor TPK | 950,000.00 | ||||||
J U M L A H (Rp.) | 26,040,000.00 | ||||||||
Pasir Bedengung, 4 Januari 2020 | |||||||||
Disetujui : | |||||||||
Kepala Desa Pasir Bedengung | Kasi Kesejahteraan | ||||||||
Bunga Citra Lovestory, SH. | Ramlee |