| RENCANA ANGGARAN BIAYA (RAB) | |||||||||
| DESA PASIR BERDENGUNG KECAMATAN PASIR LAUT | |||||||||
| TAHUN ANGGARAN 2020 | |||||||||
| Bidang | : | Pelaksanaan Pembinaan Kemasyarakatan Desa (3) | |||||||
| Sub Bidang | : | Ketenteraman, Ketertiban Umum dan Perlindungan Masyarakat (3.1.) | |||||||
| Kegiatan | : | Pengadaan Pos Keamanan Desa (Pembangunan Poskamling) (3.1.01.) | |||||||
| Pembangunan Poskamling RT. 1 RW. 2 Dusun Bahagia uk. 3 m x 2 m. 1 unit | |||||||||
| Waktu Pelaksanaan | : | 10 (sepuluh hari kalender) | |||||||
| Rincian Pendanaan | : | ||||||||
| NO. | U R A I A N | VOLUME | HARGA SATUAN (Rp) | JUMLAH (Rp) | |||||
| 1 | 2 | 3 | 4 | 5 | |||||
| I. | BAHAN | (harga hanya contoh) | |||||||
| 1 | Semen PC 50 Kg | 6.00 | Zak | 90,000 | 540,000.00 | ||||
| 2 | Semen Putih | 1.00 | Kg | 10,000 | 10,000.00 | ||||
| 3 | Pasir Beton | 1.00 | M³ | 160,000 | 160,000.00 | ||||
| 4 | Pasir Urug | 2.00 | M³ | 120,000 | 240,000.00 | ||||
| 5 | Batu Pecah 2/3 Cm | 1.00 | M³ | 500,000 | 500,000.00 | ||||
| 6 | Batako Uk. 7 x 15 x 30 Cm | 190.00 | Bh | 3,000 | 570,000.00 | ||||
| 7 | Keramik 20 x 20 cm | 5.00 | Kotak | 70,000 | 350,000.00 | ||||
| 8 | Kayu Belian 8/8 - 2 m | 6.00 | Btg | 120,000 | 720,000.00 | ||||
| 9 | Kayu Belian 8/8 - 4 m | 5.00 | Btg | 225,000 | 1,125,000.00 | ||||
| 10 | Kayu Belian 4/8 - 4 m | 3.00 | Btg | 215,000 | 645,000.00 | ||||
| 11 | Kayu Klas I 8/8 - 4 m | 3.00 | Btg | 103,000 | 309,000.00 | ||||
| 12 | Kayu Klas I 6/8 - 4 m | 1.00 | Btg | 81,000 | 81,000.00 | ||||
| 13 | Kayu Klas II 8/8 - 4 m | 3.00 | Btg | 75,000 | 225,000.00 | ||||
| 14 | Kayu Klas II 5/7 - 4 m | 6.00 | Btg | 40,000 | 240,000.00 | ||||
| 15 | Kayu Klas II 3/5 - 4 m | 10.00 | Btg | 25,000 | 250,000.00 | ||||
| 16 | Papan Mall Klas III 2/18 - 4 m | 3.00 | Kpg | 25,000 | 75,000.00 | ||||
| 17 | Papan Klas I Ketam 2/15 - 4 m | 7.00 | Kpg | 60,000 | 420,000.00 | ||||
| 18 | Amplas | 3.00 | Lbr | 5,000 | 15,000.00 | ||||
| 19 | Dempul | 3.00 | Kg | 60,000 | 180,000.00 | ||||
| 20 | Cat Tembok | 5.00 | Kg | 46,000 | 230,000.00 | ||||
| 21 | Cat Kilat/Cat Minyak | 1.00 | Kg | 60,000 | 60,000.00 | ||||
| 22 | Cat Dasar | 1.00 | Kg | 10,000 | 10,000.00 | ||||
| 23 | Thinner | 1.00 | Kg | 15,000 | 15,000.00 | ||||
| 24 | Residu/Teer | 1.00 | Ltr | 30,000 | 30,000.00 | ||||
| 25 | Baut Bangunan | 30.00 | Btg | 5,000 | 150,000.00 | ||||
| 26 | Paku Campuran | 3.00 | Kg | 25,000 | 75,000.00 | ||||
| 27 | Paku Atap | 2.00 | Kg | 25,000 | 50,000.00 | ||||
| 28 | Paku Triplek | 6.00 | Kg | 27,000 | 162,000.00 | ||||
| 29 | Seng Gelombang BJLS 0.20 | 15.00 | Lbr | 60,000 | 900,000.00 | ||||
| 30 | Seng Polos BJLS 0.30 | 1.00 | Lbr | 40,000 | 40,000.00 | ||||
| 31 | Lampu 25 Watt | 1.00 | Bh | 30,000 | 30,000.00 | ||||
| 32 | Stop Kontak | 1.00 | Bh | 25,000 | 25,000.00 | ||||
| 33 | Kabel NYM 2 x 2.5 mm | 10.00 | M' | 15,000 | 150,000.00 | ||||
| Jumlah Bahan | 8,582,000.00 | ||||||||
| II. | SEWA ALAT | ||||||||
| 1. | Gerobak Dorong | 1.00 | Bh | 200,000.00 | 200,000.00 | ||||
| Jumlah Alat | 200,000.00 | ||||||||
| III. | UPAH | ||||||||
| 1. | Pekerja | 13.00 | HOK | 85,000.00 | 1,105,000.00 | ||||
| 2. | Tukang | 17.00 | HOK | 120,000.00 | 2,040,000.00 | ||||
| 3. | Kepala Tukang | 3.00 | HOK | 140,000.00 | 420,000.00 | ||||
| 4. | Mandor | - | HOK | 120,000.00 | 0.00 | ||||
| 33.00 | HOK | Jumlah Upah | 3,565,000.00 | ||||||
| IV. | HONOR TPK | ||||||||
| 1. | Ketua | 1.00 | org | 300,000.00 | 300,000.00 | ||||
| 2. | Sekretaris | 1.00 | org | 250,000.00 | 250,000.00 | ||||
| 3. | Anggota | 2.00 | org | 200,000.00 | 400,000.00 | ||||
| (Perbup Sanggau No. 1 Thn. 2019) | |||||||||
| 4.00 | org | Jumlah Honor TPK | 950,000.00 | ||||||
| J U M L A H (Rp.) | 13,297,000.00 | ||||||||
| Pasir Bedengung, 6 Januari 2020 | |||||||||
| Disetujui : | |||||||||
| Kepala Desa Pasir Bedengung | Kasi Kesejahteraan | ||||||||
| Bunga Citra Lovestory, SH. | Ramlee | ||||||||