RENCANA ANGGARAN BIAYA (RAB) | |||||||||
DESA PASIR BERDENGUNG KECAMATAN PASIR LAUT | |||||||||
TAHUN ANGGARAN 2020 | |||||||||
Bidang | : | Pelaksanaan Pembangunan Desa (2) | |||||||
Sub Bidang | : | Kesehatan (2.2.) | |||||||
Kegiatan | : | Pembangunan Posyandu (2.2.09.) | |||||||
Paket Kegiatan | : | Pembangunan Posyandu RT. 1 RW. 2 Dusun Bahagia uk. 9 m x 5 m | |||||||
Waktu Pelaksanaan | : | 60 (enam puluh hari kalender) | |||||||
Rincian Pendanaan | : | ||||||||
NO. | U R A I A N | VOLUME | HARGA SATUAN (Rp) | JUMLAH (Rp) | |||||
1 | 2 | 3 | 4 | 5 | |||||
I. | BAHAN | (harga hanya contoh) | |||||||
1 | Semen @ 50 Kg | 174.00 | Zak | 90,000 | 15,660,000.00 | ||||
2 | Semen Putih | 77.00 | Kg | 3,000 | 231,000.00 | ||||
3 | Batu Pecah Uk. 1/2 cm | 11.00 | M3 | 400,000 | 4,400,000.00 | ||||
4 | Pasir Beton | 17.00 | M3 | 120,000 | 2,040,000.00 | ||||
5 | Pasir Urug | 16.00 | M3 | 110,000 | 1,760,000.00 | ||||
6 | Besi Beton dia. 8 mm - polos | 49.00 | Btg | 50,000 | 2,450,000.00 | ||||
7 | Besi Beton dia. 10 mm - polos | 19.00 | Btg | 85,000 | 1,615,000.00 | ||||
8 | Besi Beton dia. 12 mm - polos | 62.00 | Btg | 115,000 | 7,130,000.00 | ||||
9 | Kawat Ikat Beton/Kawat Bendrat | 17.00 | Kg | 22,000 | 374,000.00 | ||||
10 | Papan Mal uk. 1,5/15 cm | 98.00 | Kpg | 20,000 | 1,960,000.00 | ||||
11 | Cerucuk Diameter 8 cm - 4 M | 100.00 | Btg | 10,000 | 1,000,000.00 | ||||
12 | Kayu Belian Uk. 8/8 cm - 4m | 15.00 | Btg | 250,000 | 3,750,000.00 | ||||
13 | Kayu Klas II Uk. 8/12 cm - 4 m | 16.00 | Btg | 75,000 | 1,200,000.00 | ||||
14 | Kayu Klas II Uk. 6/12 cm - 4 m skoor | 27.00 | Btg | 65,000 | 1,755,000.00 | ||||
15 | Kayu Klas II Uk. 5/10 cm - 4 m | 51.00 | Btg | 55,000 | 2,805,000.00 | ||||
16 | Kayu Klas II Uk. 5/7 cm - 4 m | 57.00 | Btg | 45,000 | 2,565,000.00 | ||||
17 | Kayu Klas II Uk. 3/5 cm 4 m | 87.00 | Btg | 25,000 | 2,175,000.00 | ||||
18 | Kayu Lis Profil | 30.00 | Btg | 20,000 | 600,000.00 | ||||
19 | Papan Lisplang uk.2 x 2/18 cm - 4 m | 33.00 | Kpg | 60,000 | 1,980,000.00 | ||||
20 | Papan Perabung Uk. 1,2/18 cm - 4 m | 13.00 | Kpg | 45,000 | 585,000.00 | ||||
21 | Kayu lis profil | 10.00 | Btg | 35,000 | 350,000.00 | ||||
22 | Tutup perabung metal / Nok | 19.00 | M' | 40,000 | 760,000.00 | ||||
23 | Genteng Metal Uk. 88 cm x 88 cm | 145.00 | Lbr | 60,000 | 8,700,000.00 | ||||
24 | Plat Metal Polos | 4.00 | Lbr | 65,000 | 260,000.00 | ||||
25 | GRC | 24.00 | Lbr | 75,000 | 1,800,000.00 | ||||
26 | Batako Uk. 7 x 15 x 30 cm | 2,058.00 | Bh | 1,500 | 3,087,000.00 | ||||
27 | Keramik Uk. 30 x 30 cm | 50.00 | Kotak | 65,000 | 3,250,000.00 | ||||
28 | Keramik Uk. 20 x 20 cm | 5.00 | Kotak | 65,000 | 325,000.00 | ||||
29 | Oker Campuran | 5.00 | Kg | 17,000 | 85,000.00 | ||||
30 | Baut dia. 1/2" - 20 cm | 68.00 | Btg | 6,000 | 408,000.00 | ||||
31 | Paku GRC | 1.00 | Kg | 26,000 | 26,000.00 | ||||
32 | Paku Campuran | 19.00 | Kg | 17,000 | 323,000.00 | ||||
33 | Paku Belian | 1.00 | Kg | 22,000 | 22,000.00 | ||||
34 | Paku Metal | 1.00 | Kg | 37,000 | 37,000.00 | ||||
35 | Cat Dasar Kayu | 10.00 | Kg | 35,000 | 350,000.00 | ||||
36 | Dempul Kayu | 5.00 | Kg | 25,000 | 125,000.00 | ||||
37 | Cat Kilat | 15.00 | Kg | 40,000 | 600,000.00 | ||||
38 | Thinner | 5.00 | Ltr | 20,000 | 100,000.00 | ||||
39 | Plamur | 10.00 | Kg | 18,000 | 180,000.00 | ||||
40 | Cat Tembok | 80.00 | Kg | 50,000 | 4,000,000.00 | ||||
41 | Cat Minyak | 5.00 | Kg | 40,000 | 200,000.00 | ||||
42 | Amplas | 30.00 | Lbr | 3,000 | 90,000.00 | ||||
43 | Kunci Tanam Besar 2 x Putar | 3.00 | Bh | 150,000 | 450,000.00 | ||||
44 | Handle Pintu | 3.00 | Bh | 100,000 | 300,000.00 | ||||
45 | Engsel Pintu 4 " | 12.00 | Bh | 30,000 | 360,000.00 | ||||
46 | Engsel Jendela 3 " | 8.00 | Bh | 20,000 | 160,000.00 | ||||
47 | Kait Angin | 8.00 | Bh | 15,000 | 120,000.00 | ||||
48 | Handel Pintu | 3.00 | Set | 200,000 | 600,000.00 | ||||
49 | Handel Jendela | 13.00 | Bh | 15,000 | 195,000.00 | ||||
50 | Slot Pintu | 6.00 | Bh | 20,000 | 120,000.00 | ||||
51 | Slot Jendela | 26.00 | Bh | 10,000 | 260,000.00 | ||||
52 | Instalasi listrik | 1.00 | Unit | 3,500,000 | 3,500,000.00 | ||||
53 | Instalasi Titik Lampu dan kontak | 8.00 | Titik | 70,000 | 560,000.00 | ||||
54 | Lampu LHE 25 Watt | 4.00 | Bh | 45,000 | 180,000.00 | ||||
55 | Lampu LHE 10 Watt | 2.00 | Bh | 28,000 | 56,000.00 | ||||
56 | Fitting Duduk | 6.00 | Bh | 30,000 | 180,000.00 | ||||
57 | Stop Kontak | 3.00 | Bh | 10,000 | 30,000.00 | ||||
58 | Saklar Tunggal | 4.00 | Bh | 10,000 | 40,000.00 | ||||
59 | Saklar Ganda | 1.00 | Bh | 15,000 | 15,000.00 | ||||
60 | Pipa PVC/Pipa Kabel Dia. 1/2" | 8.00 | Btg | 20,000 | 160,000.00 | ||||
61 | Kabel NYM 3 x 2.5 | 1.00 | Rol | 350,000 | 350,000.00 | ||||
62 | Closet Jongkok | 1.00 | Bh | 250,000 | 250,000.00 | ||||
63 | Bak Air WC | 1.00 | Bh | 550,000 | 550,000.00 | ||||
64 | Tong Air 1000 L | 1.00 | Bh | 1,400,000 | 1,400,000.00 | ||||
65 | Stand link Tong Air Belian 8/8 | 1.00 | Unit | 1,500,000 | 1,500,000.00 | ||||
66 | Talang + Pengait | 1.00 | Ls | 250,000 | 250,000.00 | ||||
67 | Instalasi Air Bersih pipa PVC | 1.00 | Ls | 100,000 | 100,000.00 | ||||
68 | Kran Air WC | 1.00 | Bh | 25,000 | 25,000.00 | ||||
69 | Floor Drain | 1.00 | Bh | 20,000 | 20,000.00 | ||||
70 | Doop Penguras | 1.00 | Bh | 10,000 | 10,000.00 | ||||
71 | Beerput + instalasi air kotor | 1.00 | Unit | 1,500,000 | 1,500,000.00 | ||||
72 | Instalasi Air Bersih PVC Dia. 2" , 3/4" | 1.00 | Ls | 300,000 | 300,000.00 | ||||
73 | Instalasi Air Kotor PVC Dia. 4", 2" | 1.00 | Ls | 1,000,000 | 1,000,000.00 | ||||
74 | Pintu Kayu | 4.00 | Set | 1,000,000 | 4,000,000.00 | ||||
75 | Pintu Plastik | 1.00 | Bh | 500,000 | 500,000.00 | ||||
76 | Jendela 0.40 x 1.25 m | 13.00 | Bh | 400,000 | 5,200,000.00 | ||||
77 | Ventilasi 0,40 x 0,25 m | 13.00 | Bh | 150,000 | 1,950,000.00 | ||||
78 | Ventilasi 0,70 x 0,25 m | 4.00 | Bh | 250,000 | 1,000,000.00 | ||||
79 | Ventilasi (karawang) | 12.00 | Bh | 15,000 | 180,000.00 | ||||
80 | Dipan, matras & bantal | 1.00 | Set | 1,000,000 | 1,000,000.00 | ||||
81 | Meja Kerja | 1.00 | Bh | 500,000 | 500,000.00 | ||||
82 | Meja Layanan Posyandu | 5.00 | Bh | 300,000 | 1,500,000.00 | ||||
83 | Kursi Petugas/ Kader | 6.00 | Bh | 300,000 | 1,800,000.00 | ||||
84 | Kursi Plastik | 30.00 | Bh | 100,000 | 3,000,000.00 | ||||
85 | Lemari Arsip | 1.00 | Bh | 400,000 | 400,000.00 | ||||
86 | Kipas Angin Tempel | 5.00 | Bh | 500,000 | 2,500,000.00 | ||||
87 | Timbangan Dacin Posyandu (sarung) | 1.00 | Bh | 600,000 | 600,000.00 | ||||
88 | Timbangan Balita Baring | 1.00 | Bh | 400,000 | 400,000.00 | ||||
Jumlah Bahan | 120,003,000.00 | ||||||||
II. | SEWA ALAT (sesuai keperluan) | ||||||||
1. | Gerobak Dorong | 2.00 | Bh | 200,000.00 | 400,000.00 | ||||
Jumlah Alat | 400,000.00 | ||||||||
III. | UPAH | ||||||||
1. | Pekerja | 102.00 | HOK | 85,000.00 | 8,670,000.00 | ||||
2. | Tukang | 67.00 | HOK | 120,000.00 | 8,040,000.00 | ||||
3. | Kepala Tukang | 17.00 | HOK | 140,000.00 | 2,380,000.00 | ||||
4. | Mandor | 8.00 | HOK | 120,000.00 | 960,000.00 | ||||
194.00 | HOK | Jumlah Upah | 20,050,000.00 | ||||||
IV. | HONOR TPK | ||||||||
1. | Ketua | 1.00 | org | 450,000.00 | 450,000.00 | ||||
2. | Sekretaris | 1.00 | org | 400,000.00 | 400,000.00 | ||||
3. | Anggota | 3.00 | org | 350,000.00 | 1,050,000.00 | ||||
(Perbup Sanggau No. 1 Thn. 2019) | |||||||||
5.00 | org | Jumlah Honor TPK | 1,900,000.00 | ||||||
J U M L A H (Rp.) | 142,353,000.00 | ||||||||
Pasir Bedengung, 26 Desember 2019 | |||||||||
Disetujui : | |||||||||
Kepala Desa Pasir Bedengung | Kasi Kesejahteraan | ||||||||
Bunga Citra Lovestory, SH. | Ramlee |