KOEFISIEN ANALISIS HARGA SATUAN PEKERJAAN (AHSP) |
PEMBUATAN BETON |
BERDASARKAN AHSP BIDANG PEKERJAAN UMUM TAHUN 2012 |
| | | | |
A.3. PEKERJAAN BETON (halaman 115) |
A.3.1. Koefisien untuk AHSP pembuatan beton |
A.3.1. B.01. 1 m3 beton untuk lantai kerja (bedding) |
| |
No. | Uraian | Satuan | Koefisien |
|
A. | TENAGA | | | |
1 | Pekerja | OH | 1.200 |
2 | Tukang Batu | OH | 0.200 |
3 | Kepala Tukang | OH | 0.020 |
4 | Mandor | OH | 0.060 |
| | | | |
B. | BAHAN | | | |
1 | Portland Cement | kg | 230 (4,60 zak) |
2 | Pasir Beton | kg | 893 (0,638 m3) |
3 | Batu Pecah (maks. 30 mm) | kg | 1.027 (0,761 m3) |
4 | Air | liter | 215 |
| | | | |
C. | PERALATAN | | | |
| | | | |
Catatan : Berat isi pasir beton | 1,400 | kg/m3 | |
Berat isi split/kerikil | 1,350 | kg/m3 | |
| | | | |
A.3.1. B.02. 1 m3 beton mutu f'c = 7,4 MPa (K-100), w/c = 0,87 |
| |
No. | Uraian | Satuan | Koefisien |
| Manual | Molen |
A. | TENAGA | | | |
1 | Pekerja | OH | 1.650 | 1.320 |
2 | Tukang Batu | OH | 0.275 | 0.205 |
3 | Kepala Tukang | OH | 0.028 | 0.020 |
4 | Mandor | OH | 0.083 | 0.060 |
| | | | |
B. | BAHAN | | | |
1 | Portland Cement | kg | 247 (4,94 zak) |
2 | Pasir Beton | kg | 869 (0,638 m3) |
3 | Batu Pecah (maks. 30 mm) | kg | 999 (0,761 m3) |
4 | Air | liter | 215 |
| | | | |
C. | PERALATAN | | | |
1 | Molen 0,35 m3 | hari | | 0.200 |
Catatan : Berat isi pasir beton | 1,400 | kg/m3 | |
Berat isi split/kerikil | 1,350 | kg/m3 | |
| | | | |
A.3.1. B.03. 1 m3 beton mutu f'c = 9,8 MPa (K-125), w/c = 0,78 |
| |
No. | Uraian | Satuan | Koefisien |
| Manual | Molen |
A. | TENAGA | | | |
1 | Pekerja | OH | 1.650 | 1.320 |
2 | Tukang Batu | OH | 0.275 | 0.205 |
3 | Kepala Tukang | OH | 0.028 | 0.020 |
4 | Mandor | OH | 0.083 | 0.060 |
| | | | |
B. | BAHAN | | | |
1 | Portland Cement | kg | 279 (5,58 zak) |
2 | Pasir Beton | kg | 828 (0,591 m3) |
3 | Batu Pecah (maks. 30 mm) | kg | 1.012 (0,750 m3) |
4 | Air | liter | 215 |
| | | | |
C. | PERALATAN | | | |
1 | Molen 0,35 m3 | hari | | 0.200 |
Catatan : Berat isi pasir beton | 1,400 | kg/m3 | |
Berat isi split/kerikil | 1,350 | kg/m3 | |
| | | | |
A.3.1. B.04. 1 m3 beton mutu f'c = 12,2 MPa (K-150), w/c = 0,72 |
| |
No. | Uraian | Satuan | Koefisien |
| Manual | Molen |
A. | TENAGA | | | |
1 | Pekerja | OH | 1.650 | 1.320 |
2 | Tukang Batu | OH | 0.275 | 0.205 |
3 | Kepala Tukang | OH | 0.028 | 0.020 |
4 | Mandor | OH | 0.083 | 0.060 |
| | | | |
B. | BAHAN | | | |
1 | Portland Cement | kg | 299 (5,98 zak) |
2 | Pasir Beton | kg | 799 (0,571 m3) |
3 | Batu Pecah (maks. 30 mm) | kg | 1.017 (0,753 m3) |
4 | Air | liter | 215 |
| | | | |
C. | PERALATAN | | | |
1 | Molen 0,35 m3 | hari | | 0.200 |
Catatan : Berat isi pasir beton | 1,400 | kg/m3 | |
Berat isi split/kerikil | 1,350 | kg/m3 | |
| | | | |
A.3.1. B.05. 1 m3 beton mutu f'c = 14,5 MPa (K-175), w/c = 0,66 |
| |
No. | Uraian | Satuan | Koefisien |
| Manual | Molen |
A. | TENAGA | | | |
1 | Pekerja | OH | 1.650 | 1.320 |
2 | Tukang Batu | OH | 0.275 | 0.205 |
3 | Kepala Tukang | OH | 0.028 | 0.020 |
4 | Mandor | OH | 0.083 | 0.060 |
| | | | |
B. | BAHAN | | | |
1 | Portland Cement | kg | 326 (6,52 zak) |
2 | Pasir Beton | kg | 760 (0,543 m3) |
3 | Batu Pecah (maks. 30 mm) | kg | 1.029 (0,762 m3) |
4 | Air | liter | 215 |
| | | | |
C. | PERALATAN | | | |
1 | Molen 0,35 m3 | hari | | 0.200 |
Catatan : Berat isi pasir beton | 1,400 | kg/m3 | |
Berat isi split/kerikil | 1,350 | kg/m3 | |
| | | | |
A.3.1. B.06. 1 m3 beton mutu f'c = 16,9 MPa (K-200), w/c = 0,61 |
| |
No. | Uraian | Satuan | Koefisien |
| Manual | Molen |
A. | TENAGA | | | |
1 | Pekerja | OH | 1.650 | 1.320 |
2 | Tukang Batu | OH | 0.275 | 0.205 |
3 | Kepala Tukang | OH | 0.028 | 0.020 |
4 | Mandor | OH | 0.083 | 0.060 |
| | | | |
B. | BAHAN | | | |
1 | Portland Cement | kg | 352 (7,04 zak) |
2 | Pasir Beton | kg | 731 (0,522 m3) |
3 | Batu Pecah (maks. 30 mm) | kg | 1.031 (0,764 m3) |
4 | Air | liter | 215 |
| | | | |
C. | PERALATAN | | | |
1 | Molen 0,35 m3 | hari | | 0.200 |
Catatan : Berat isi pasir beton | 1,400 | kg/m3 | |
Berat isi split/kerikil | 1,350 | kg/m3 | |
| | | | |
A.3.1. B.07. 1 m3 beton mutu f'c = 19,3 MPa (K-225), w/c = 0,58 |
| |
No. | Uraian | Satuan | Koefisien |
| Manual | Molen |
A. | TENAGA | | | |
1 | Pekerja | OH | 1.650 | 1.320 |
2 | Tukang Batu | OH | 0.275 | 0.205 |
3 | Kepala Tukang | OH | 0.028 | 0.020 |
4 | Mandor | OH | 0.083 | 0.060 |
| | | | |
B. | BAHAN | | | |
1 | Portland Cement | kg | 371 (7,42 zak) |
2 | Pasir Beton | kg | 698 (0,499 m3) |
3 | Batu Pecah (maks. 30 mm) | kg | 1.047 (0,776 m3) |
4 | Air | liter | 215 |
| | | | |
C. | PERALATAN | | | |
1 | Molen 0,35 m3 | hari | | 0.200 |
Catatan : Berat isi pasir beton | 1,400 | kg/m3 | |
Berat isi split/kerikil | 1,350 | kg/m3 | |
| | | | |
A.3.1. B.08. 1 m3 beton mutu f'c = 21,7 MPa (K-250), w/c = 0,56 |
| |
No. | Uraian | Satuan | Koefisien |
| Manual | Molen |
A. | TENAGA | | | |
1 | Pekerja | OH | 1.650 | 1.320 |
2 | Tukang Batu | OH | 0.275 | 0.205 |
3 | Kepala Tukang | OH | 0.028 | 0.020 |
4 | Mandor | OH | 0.083 | 0.060 |
| | | | |
B. | BAHAN | | | |
1 | Portland Cement | kg | 384 (7,68 zak) |
2 | Pasir Beton | kg | 692 (0,494 m3) |
3 | Batu Pecah (maks. 30 mm) | kg | 1.039 (0,770 m3) |
4 | Air | liter | 215 |
| | | | |
C. | PERALATAN | | | |
1 | Molen 0,35 m3 | hari | | 0.200 |
Catatan : Berat isi pasir beton | 1,400 | kg/m3 | |
Berat isi split/kerikil | 1,350 | kg/m3 | |
| | | | |
A.3.1. B.09. 1 m3 beton mutu f'c = 24,0 MPa (K-275), w/c = 0,53 |
| |
No. | Uraian | Satuan | Koefisien |
| Manual | Molen |
A. | TENAGA | | | |
1 | Pekerja | OH | 1.650 | 1.320 |
2 | Tukang Batu | OH | 0.275 | 0.205 |
3 | Kepala Tukang | OH | 0.028 | 0.020 |
4 | Mandor | OH | 0.083 | 0.060 |
| | | | |
B. | BAHAN | | | |
1 | Portland Cement | kg | 406 (8,12 zak) |
2 | Pasir Beton | kg | 684 (0,489 m3) |
3 | Batu Pecah (maks. 30 mm) | kg | 1.026 (0,760 m3) |
4 | Air | liter | 215 |
| | | | |
C. | PERALATAN | | | |
1 | Molen 0,35 m3 | hari | | 0.200 |
Catatan : Berat isi pasir beton | 1,400 | kg/m3 | |
Berat isi split/kerikil | 1,350 | kg/m3 | |
| | | | |
A.3.1. B.10. 1 m3 beton mutu f'c = 26,4 MPa (K-300), w/c = 0,52 |
| |
No. | Uraian | Satuan | Koefisien |
| Manual | Molen |
A. | TENAGA | | | |
1 | Pekerja | OH | 1.650 | 1.320 |
2 | Tukang Batu | OH | 0.275 | 0.205 |
3 | Kepala Tukang | OH | 0.028 | 0.020 |
4 | Mandor | OH | 0.083 | 0.060 |
| | | | |
B. | BAHAN | | | |
1 | Portland Cement | kg | 413 (8,26 zak) |
2 | Pasir Beton | kg | 681 (0,486 m3) |
3 | Batu Pecah (maks. 30 mm) | kg | 1.021 (0,756 m3) |
4 | Air | liter | 215 |
| | | | |
C. | PERALATAN | | | |
1 | Molen 0,35 m3 | hari | | 0.200 |
Catatan : Berat isi pasir beton | 1,400 | kg/m3 | |
Berat isi split/kerikil | 1,350 | kg/m3 | |
| | | | |
A.3.1. B.11. 1 m3 beton mutu f'c = 28,8 MPa (K-325), w/c = 0,49 |
| |
No. | Uraian | Satuan | Koefisien |
| Manual | Molen |
A. | TENAGA | | | |
1 | Pekerja | OH | 1.650 | 1.320 |
2 | Tukang Batu | OH | 0.275 | 0.205 |
3 | Kepala Tukang | OH | 0.028 | 0.020 |
4 | Mandor | OH | 0.083 | 0.060 |
| | | | |
B. | BAHAN | | | |
1 | Portland Cement | kg | 439 (8,78 zak) |
2 | Pasir Beton | kg | 670 (0,479 m3) |
3 | Batu Pecah (maks. 30 mm) | kg | 1.006 (0,745 m3) |
4 | Air | liter | 215 |
| | | | |
C. | PERALATAN | | | |
1 | Molen 0,35 m3 | hari | | 0.200 |
Catatan : Berat isi pasir beton | 1,400 | kg/m3 | |
Berat isi split/kerikil | 1,350 | kg/m3 | |
| | | | |
A.3.1. B.12. 1 m3 beton mutu f'c = 31,2 MPa (K-350), w/c = 0,48 |
| |
No. | Uraian | Satuan | Koefisien |
| Manual | Molen |
A. | TENAGA | | | |
1 | Pekerja | OH | 1.650 | 1.320 |
2 | Tukang Batu | OH | 0.275 | 0.205 |
3 | Kepala Tukang | OH | 0.028 | 0.020 |
4 | Mandor | OH | 0.083 | 0.060 |
| | | | |
B. | BAHAN | | | |
1 | Portland Cement | kg | 448 (8,96 zak) |
2 | Pasir Beton | kg | 667 (0,476 m3) |
3 | Batu Pecah (maks. 30 mm) | kg | 1.000 (0,741 m3) |
4 | Air | liter | 215 |
| | | | |
C. | PERALATAN | | | |
1 | Molen 0,35 m3 | hari | | 0.200 |
Catatan : Berat isi pasir beton | 1,400 | kg/m3 | |
Berat isi split/kerikil | 1,350 | kg/m3 | |
w/c = water/cement = faktor air semen | |
MPa = MegaPascal = satuan tekanan | |