| RENCANA ANGGARAN BIAYA (RAB) | |||||||||
| DESA PASIR BERDENGUNG KECAMATAN PASIR LAUT | |||||||||
| TAHUN ANGGARAN 2020 | |||||||||
| Bidang | : | Pelaksanaan Pembangunan Desa (2) | |||||||
| Sub Bidang | : | Pekerjaan Umum dan Penataan Ruang (2.3.) | |||||||
| Kegiatan | : | Pembangunan Jalan Lingkungan Permukiman (2.3.11.) | |||||||
| Jalan Rabat Beton (Mutu K-100) RT. 1 RW. 2 Dsn. Bahagia uk. 100 m x 2 m x 0,1 m | |||||||||
| Waktu Pelaksanaan | : | 30 (tiga puluh hari kalender) | |||||||
| Rincian Pendanaan | : | ||||||||
| NO. | U R A I A N | VOLUME | HARGA SATUAN (Rp) | JUMLAH (Rp) | |||||
| 1 | 2 | 3 | 4 | 5 | |||||
| I. | BAHAN | (Harga hanya contoh) | |||||||
| 1. | Semen (1 zak=50 kg) | 99.00 | Zak | 90,000.00 | 8,910,000.00 | ||||
| 2. | Pasir Beton | 13.00 | M3 | 140,000.00 | 1,820,000.00 | ||||
| 3. | Pasir Urug | 12.00 | M3 | 120,000.00 | 1,440,000.00 | ||||
| 4. | Batu pecah 2/3 cm (kerikil) | 15.00 | M3 | 500,000.00 | 7,500,000.00 | ||||
| 5. | Papan Mal uk. 2/18 cm- 4m | 25.00 | Kpg | 22,000.00 | 550,000.00 | ||||
| 6. | Plastik untuk Alas Cor Beton | 220.00 | M2 | 4,000.00 | 880,000.00 | ||||
| 7. | Kayu Reng | 7.00 | Btg | 15,000.00 | 105,000.00 | ||||
| 8. | Paku Campur | 2.00 | Kg | 22,000.00 | 44,000.00 | ||||
| Jumlah Bahan | 21,249,000.00 | ||||||||
| II. | SEWA ALAT (sesuai keperluan) | ||||||||
| 1. | Gerobak Dorong | 2.00 | Bh | 200,000.00 | 400,000.00 | ||||
| Jumlah Alat | 400,000.00 | ||||||||
| III. | UPAH | ||||||||
| 1. | Pekerja | 49.00 | HOK | 85,000.00 | 4,165,000.00 | ||||
| 2. | Tukang | 9.00 | HOK | 120,000.00 | 1,080,000.00 | ||||
| 3. | Kepala Tukang | 1.00 | HOK | 140,000.00 | 140,000.00 | ||||
| 4. | Mandor | 3.00 | HOK | 120,000.00 | 360,000.00 | ||||
| 62.00 | HOK | Jumlah Upah | 5,745,000.00 | ||||||
| IV. | HONOR TPK | ||||||||
| 1. | Ketua | 1.00 | org | 300,000.00 | 300,000.00 | ||||
| 2. | Sekretaris | 1.00 | org | 250,000.00 | 250,000.00 | ||||
| 3. | Anggota | 2.00 | org | 200,000.00 | 400,000.00 | ||||
| (Perbup Sanggau No. 1 Thn. 2019) | |||||||||
| 4.00 | org | Jumlah Honor TPK | 950,000.00 | ||||||
| J U M L A H (Rp.) | 28,344,000.00 | ||||||||
| Pasir Bedengung, 12 November 2019 | |||||||||
| Disetujui : | |||||||||
| Kepala Desa Pasir Bedengung | Kasi Kesejahteraan | ||||||||
| Bunga Citra Lovestory, SH. | Ramlee | ||||||||