RENCANA ANGGARAN BIAYA (RAB) | |||||||||
DESA PASIR BERDENGUNG KECAMATAN PASIR LAUT | |||||||||
TAHUN ANGGARAN 2020 | |||||||||
Bidang | : | Pelaksanaan Pembangunan Desa (2) | |||||||
Sub Bidang | : | Pekerjaan Umum dan Penataan Ruang (2.3.) | |||||||
Kegiatan | : | Pembangunan Prasarana Jalan Desa (Drainase) (2.3.14.) | |||||||
Drainase Beton RT. 1 RW. 2 Dusun Bahagia ukuran 0,3 m x 0,4 m x 400 m | |||||||||
Waktu Pelaksanaan | : | 30 (tiga puluh hari kalender) | |||||||
Rincian Pendanaan | : | ||||||||
NO. | U R A I A N | VOLUME | HARGA SATUAN (Rp) | JUMLAH (Rp) | |||||
1 | 2 | 3 | 4 | 5 | |||||
I. | BAHAN | (Harga hanya contoh) | |||||||
1. | Semen (1 zak=50 kg) | 288.00 | Zak | 100,000.00 | 28,800,000.00 | ||||
2. | Pasir Beton | 31.00 | M3 | 200,000.00 | 6,200,000.00 | ||||
3. | Pasir Urug | 20.00 | M3 | 150,000.00 | 3,000,000.00 | ||||
4. | Batu Pecah/Kerikil | 39.00 | M3 | 250,000.00 | 9,750,000.00 | ||||
5. | Papan Mal uk. 2/18 cm-4m | 288.00 | Kpg | 30,000.00 | 8,640,000.00 | ||||
6. | Kayu 4/6 | 288.00 | Btg | 25,000.00 | 7,200,000.00 | ||||
7. | Paku Campur | 80.00 | Kg | 20,000.00 | 1,600,000.00 | ||||
8. | Plastik untuk Alas Cor Beton | 600.00 | M2 | 5,000.00 | 3,000,000.00 | ||||
Jumlah Bahan | 68,190,000.00 | ||||||||
II. | SEWA ALAT (sesuai keperluan) | ||||||||
1. | Gerobak Dorong | 2.00 | Bh | 200,000.00 | 400,000.00 | ||||
2. | Sewa concrete mixer (molen) | 11.00 | hari | 400,000.00 | 4,400,000.00 | ||||
Jumlah Alat | 4,800,000.00 | ||||||||
III. | UPAH (include galian tanah) | ||||||||
1. | Pekerja | 130.00 | HOK | 125,000.00 | 16,250,000.00 | ||||
2. | Tukang | 11.00 | HOK | 140,000.00 | 1,540,000.00 | ||||
3. | Kepala Tukang | 2.00 | HOK | 150,000.00 | 300,000.00 | ||||
4. | Mandor | 15.00 | HOK | 150,000.00 | 2,250,000.00 | ||||
158.00 | HOK | Jumlah Upah | 20,340,000.00 | ||||||
IV. | HONOR TPK | ||||||||
1. | Ketua | 1.00 | org | 450,000.00 | 450,000.00 | ||||
2. | Sekretaris | 1.00 | org | 400,000.00 | 400,000.00 | ||||
3. | Anggota | 3.00 | org | 350,000.00 | 1,050,000.00 | ||||
(Perbup Sanggau No. 1 Thn. 2019) | |||||||||
5.00 | org | Jumlah Honor TPK | 1,900,000.00 | ||||||
J U M L A H (Rp.) | 95,230,000.00 |