| RENCANA ANGGARAN BIAYA (RAB) | |||||||||
| DESA PASIR BERDENGUNG KECAMATAN PASIR LAUT | |||||||||
| TAHUN ANGGARAN 2020 | |||||||||
| Bidang | : | Pelaksanaan Pembangunan Desa (2) | |||||||
| Sub Bidang | : | Kawasan Permukiman (2.4.) | |||||||
| Kegiatan | : | Pembangunan Jamban Umum (2.4.14.) | |||||||
| Pembangunan Jamban Umum RT. 1 RW. 2 Dusun Bahagia uk. 3 m x 2 m. 1 unit | |||||||||
| Waktu Pelaksanaan | : | 10 (sepuluh hari kalender) | |||||||
| Rincian Pendanaan | : | ||||||||
| NO. | U R A I A N | VOLUME | HARGA SATUAN (Rp) | JUMLAH (Rp) | |||||
| 1 | 2 | 3 | 4 | 5 | |||||
| I. | BAHAN | (harga hanya contoh) | |||||||
| 1 | Semen PC 50 Kg | 12.00 | Zak | 90,000 | 1,080,000.00 | ||||
| 2 | Semen Putih | 1.00 | Kg | 10,000 | 10,000.00 | ||||
| 3 | Pasir Beton | 5.00 | M³ | 160,000 | 800,000.00 | ||||
| 4 | Pasir Urug | 4.00 | M³ | 120,000 | 480,000.00 | ||||
| 5 | Batu Pecah 2/3 Cm | 2.00 | M³ | 500,000 | 1,000,000.00 | ||||
| 6 | Batako Uk. 7 x 15 x 30 Cm | 117.00 | Bh | 2,500 | 292,500.00 | ||||
| 7 | Keramik 20 x 20 cm | 9.00 | Kotak | 70,000 | 630,000.00 | ||||
| 8 | Kayu Belian 9/9 - 4 m | 17.00 | Btg | 260,000 | 4,420,000.00 | ||||
| 9 | Kayu Belian 8/8 - 4 m (ketam) | 15.00 | Btg | 205,000 | 3,075,000.00 | ||||
| 10 | Kayu Belian 4/8 - 4 m | 5.00 | Btg | 215,000 | 1,075,000.00 | ||||
| 11 | Kayu Klas I 8/8 - 4 m | 14.00 | Btg | 103,000 | 1,442,000.00 | ||||
| 12 | Kayu Klas I 5/10 - 4 m | 5.00 | Btg | 81,000 | 405,000.00 | ||||
| 13 | Kayu Klas II 8/12 - 4 m | 8.00 | Btg | 75,000 | 600,000.00 | ||||
| 14 | Kayu Klas II 5/7 - 4 m | 6.00 | Btg | 40,000 | 240,000.00 | ||||
| 15 | Kayu Klas II 4/6 - 4 m | 7.00 | Btg | 25,000 | 175,000.00 | ||||
| 16 | Kayu Klas II 2/3 - 4 m | 15.00 | Btg | 66,000 | 990,000.00 | ||||
| 17 | Papan Mall Klas III 2/18 - 4 m | 4.00 | Kpg | 32,000 | 128,000.00 | ||||
| 18 | Papan Belian tdk ketam 2/18 - 4 m | 21.00 | Kpg | 24,000 | 504,000.00 | ||||
| 19 | Papan Klas I Ketam 2/15 - 4 m | 12.00 | Kpg | 15,000 | 180,000.00 | ||||
| 20 | Amplas | 10.00 | Lbr | 5,000 | 50,000.00 | ||||
| 21 | Dempul | 6.00 | Kg | 60,000 | 360,000.00 | ||||
| 22 | Cat Tembok | 5.00 | Kg | 46,000 | 230,000.00 | ||||
| 23 | Cat Kilat/Cat Minyak | 15.00 | Kg | 60,000 | 900,000.00 | ||||
| 24 | Cat Dasar | 11.00 | Kg | 10,000 | 110,000.00 | ||||
| 25 | Thinner | 1.00 | Kg | 15,000 | 15,000.00 | ||||
| 26 | Residu/Teer | 1.00 | Ltr | 30,000 | 30,000.00 | ||||
| 27 | Besi tulangan dia. 8 mm-12m | 6.00 | Btg | 75,000 | 450,000.00 | ||||
| 28 | Kawat Bendrat | 1.00 | Btg | 25,000 | 25,000.00 | ||||
| 29 | Besi Beugel | 4.00 | Btg | 27,000 | 108,000.00 | ||||
| 30 | Baut Bangunan | 50.00 | Btg | 5,000 | 250,000.00 | ||||
| 31 | Paku Campuran | 12.50 | Kg | 20,000 | 250,000.00 | ||||
| 32 | Paku Atap | 2.00 | Kg | 20,000 | 40,000.00 | ||||
| 33 | Paku Triplek | 3.00 | Kg | 22,000 | 66,000.00 | ||||
| 34 | Kunci Pintu Tanam | 2.00 | set | 150,000 | 300,000.00 | ||||
| 35 | Engsel Pintu | 6.00 | set | 50,000 | 300,000.00 | ||||
| 36 | Seng Gelombang BJLS 0.20 | 18.00 | Lbr | 60,000 | 1,080,000.00 | ||||
| 37 | Seng Polos BJLS 0.30 | 3.00 | Lbr | 40,000 | 120,000.00 | ||||
| 38 | Tutup Perabung Metal | 12.00 | M' | 50,000 | 600,000.00 | ||||
| 39 | Pintu Panel Kayu Belian | 2.00 | Bh | 10,000 | 20,000.00 | ||||
| 40 | Ventilasi Jalusi | 8.00 | set | 10,000 | 80,000.00 | ||||
| 41 | Triplek 3 mm | 4.00 | Lbr | 80,000 | 320,000.00 | ||||
| 42 | Closet Jongkok | 2.00 | Bh | 60,000 | 120,000.00 | ||||
| 43 | Kran Air | 2.00 | Bh | 15,000 | 30,000.00 | ||||
| 44 | Floor Drain | 2.00 | Bh | 30,000 | 60,000.00 | ||||
| 45 | Pipa PVC 4" | 2.00 | Btg | 350,000 | 700,000.00 | ||||
| 46 | Pipa PVC 2" | 4.00 | Btg | 250,000 | 1,000,000.00 | ||||
| 47 | Pipa Galvanis 2" | 1.00 | Btg | 200,000 | 200,000.00 | ||||
| 48 | Lem Pralon | 1.00 | Bh | 25,000 | 25,000.00 | ||||
| 49 | Talang Air | 1.00 | Bh | 60,000 | 60,000.00 | ||||
| 50 | Tong Air isi 1000 ltr | 1.00 | Bh | 1,700,000 | 1,700,000.00 | ||||
| 51 | Sambungan Pipa | 6.00 | Bh | 10,000 | 60,000.00 | ||||
| 52 | Lampu 25 Watt | 3.00 | Bh | 30,000 | 90,000.00 | ||||
| 53 | Stop Kontak | 3.00 | Bh | 25,000 | 75,000.00 | ||||
| 54 | Kabel NYM 2 x 2.5 mm | 10.00 | M' | 15,000 | 150,000.00 | ||||
| Jumlah Bahan | 27,500,500.00 | ||||||||
| II. | SEWA ALAT (sesuai keperluan) | ||||||||
| 1. | Gerobak Dorong | 4.00 | Bh | 200,000.00 | 800,000.00 | ||||
| Jumlah Alat | 800,000.00 | ||||||||
| III. | UPAH | ||||||||
| 1. | Pekerja | 32.00 | HOK | 85,000.00 | 2,720,000.00 | ||||
| 2. | Tukang | 24.00 | HOK | 120,000.00 | 2,880,000.00 | ||||
| 3. | Kepala Tukang | 5.00 | HOK | 140,000.00 | 700,000.00 | ||||
| 4. | Mandor | - | HOK | 120,000.00 | 0.00 | ||||
| 61.00 | HOK | Jumlah Upah | 6,300,000.00 | ||||||
| IV. | HONOR TPK | ||||||||
| 1. | Ketua | 1.00 | org | 300,000.00 | 300,000.00 | ||||
| 2. | Sekretaris | 1.00 | org | 250,000.00 | 250,000.00 | ||||
| 3. | Anggota | 2.00 | org | 200,000.00 | 400,000.00 | ||||
| (Perbup Sanggau No. 1 Thn. 2019) | |||||||||
| 4.00 | org | Jumlah Honor TPK | 950,000.00 | ||||||
| J U M L A H (Rp.) | 35,550,500.00 | ||||||||
| Pasir Bedengung, 28 Oktober 2019 | |||||||||
| Disetujui : | |||||||||
| Kepala Desa Pasir Bedengung | Kasi Kesejahteraan | ||||||||
| Bunga Citra Lovestory, SH. | Ramlee | ||||||||
Tag Terpopuler
Desain dan RAB Pembangunan WC (Jamban) Umum
Admin
Minggu, 27 Oktober 2019 | Oktober 27, 2019 WIB
Last Updated
2022-07-12T12:03:51Z