RENCANA ANGGARAN BIAYA (RAB) | |||||||||
DESA PASIR BERDENGUNG KECAMATAN PASIR LAUT | |||||||||
TAHUN ANGGARAN 2020 | |||||||||
Bidang | : | Pelaksanaan Pembangunan Desa (2) | |||||||
Sub Bidang | : | Pekerjaan Umum dan Penataan Ruang (2.3.) | |||||||
Kegiatan | : | Pembangunan Jembatan Milik Desa ** (2.3.13.) | |||||||
Pembangunan Jembatan Beton RT. 1 RW. 2 Dusun Bahagia ukuran 6 m x 4 m | |||||||||
Waktu Pelaksanaan | : | 30 (Tiga Puluh Hari Kalender) | |||||||
Rincian Pendanaan | : | ||||||||
NO. | U R A I A N | VOLUME | HARGA SATUAN (Rp) | JUMLAH (Rp) | |||||
1 | 2 | 3 | 4 | 5 | |||||
I. | BAHAN | (harga hanya contoh) | |||||||
1. | Semen (1 zak=50 kg) | 139.00 | zak | 90,000.00 | 12,510,000.00 | ||||
2. | Pasir beton | 12.00 | M3 | 150,000.00 | 1,800,000.00 | ||||
3. | Pasir urug | 2.00 | M3 | 140,000.00 | 280,000.00 | ||||
4. | Batu pecah 1/2 cm | 17.00 | M3 | 500,000.00 | 8,500,000.00 | ||||
5. | Besi beton ulir dia. 13 mm- 12 m | 18.00 | Btg | 165,000.00 | 2,970,000.00 | ||||
6. | Besi beton polos dia. 12 mm- 12 m | 24.00 | Btg | 115,000.00 | 2,760,000.00 | ||||
7. | Besi beton polos dia. 10 mm - 12 m | 119.00 | Btg | 85,000.00 | 10,115,000.00 | ||||
8. | Besi beton polos dia. 8 mm - 12 m | 60.00 | Btg | 50,000.00 | 3,000,000.00 | ||||
9. | Kawat beton (bendrat) | 22.00 | Kg | 23,000.00 | 506,000.00 | ||||
10. | Papan mal uk. 2/18 cm- 4m | 127.00 | Kpg | 25,000.00 | 3,175,000.00 | ||||
11. | Kayu perancah bulat | 100.00 | Btg | 10,000.00 | 1,000,000.00 | ||||
12. | Kayu perancah 4/6 - 4m | 30.00 | Btg | 25,000.00 | 750,000.00 | ||||
13. | Paku campur | 22.00 | Kg | 25,000.00 | 550,000.00 | ||||
14. | Plastik cor | 92.00 | M2 | 5,000.00 | 460,000.00 | ||||
15. | Cerucuk pondasi dia.10 cm- 4 m | 40.00 | Btg | 15,000.00 | 600,000.00 | ||||
16. | Cat minyak 2 warna | 10.00 | Kg | 60,000.00 | 600,000.00 | ||||
17. | Thinner pengencer | 1.00 | Klg | 90,000.00 | 90,000.00 | ||||
18. | Dempul (untuk lening jembatan) | 2.00 | Klg | 50,000.00 | 100,000.00 | ||||
Jumlah Bahan | 49,766,000.00 | ||||||||
II. | SEWA ALAT (sesuai keperluan) | ||||||||
1. | Gerobak Dorong | 4.00 | Bh | 200,000.00 | 800,000.00 | ||||
2. | Concrete mixer (molen) & operasional | 5.00 | hari | 400,000.00 | 2,000,000.00 | ||||
Jumlah Alat | 2,800,000.00 | ||||||||
III. | UPAH | ||||||||
1. | Pekerja | 91.00 | HOK | 85,000.00 | 7,735,000.00 | ||||
2. | Tukang | 35.00 | HOK | 120,000.00 | 4,200,000.00 | ||||
3. | Kepala Tukang | 4.00 | HOK | 140,000.00 | 560,000.00 | ||||
4. | Mandor | 7.00 | HOK | 120,000.00 | 840,000.00 | ||||
137.00 | HOK | Jumlah Upah | 13,335,000.00 | ||||||
IV. | HONOR TPK | ||||||||
1. | Ketua | 1.00 | org | 450,000.00 | 450,000.00 | ||||
2. | Sekretaris | 1.00 | org | 400,000.00 | 400,000.00 | ||||
3. | Anggota | 2.00 | org | 350,000.00 | 700,000.00 | ||||
(Perbup Sanggau No. 1 Thn. 2019) | |||||||||
4.00 | org | Jumlah Honor TPK | 1,550,000.00 | ||||||
J U M L A H (Rp.) | 67,451,000.00 |
LIHAT JUGA: Cara Menghitung Komposisi Campuran Beton Mutu K-225
BACA JUGA : Cara Menghitung Komposisi Campuran Beton Mutu K-100 untuk Lantai Kerja
BACA JUGA : Koefisien (Indeks) Bahan, Upah & Alat Pekerjaan Beton
BACA JUGA : Koefisien (Indeks) Bahan, Upah & Alat Pekerjaan Beton