RENCANA ANGGARAN BIAYA (RAB) | |||||||||
DESA PASIR BERDENGUNG KECAMATAN PASIR LAUT | |||||||||
TAHUN ANGGARAN 2020 | |||||||||
Bidang | : | Pelaksanaan Pembangunan Desa (2) | |||||||
Sub Bidang | : | Pekerjaan Umum dan Penataan Ruang (2.3.) | |||||||
Kegiatan | : | Pembangunan Prasarana Jalan Desa (Prasarana Jalan Lain) (2.3.14.) | |||||||
Pasangan Batu RT. 1 RW. 2 Dsn. Bahagia uk. 0,3 m x 0,8 m x 1,75 m x 50 m | |||||||||
Waktu Pelaksanaan | : | 30 (tiga puluh hari kalender) | |||||||
Rincian Pendanaan | : | ||||||||
NO. | U R A I A N | VOLUME | HARGA SATUAN (Rp) | JUMLAH (Rp) | |||||
1 | 2 | 3 | 4 | 5 | |||||
I. | BAHAN | (Harga hanya contoh) | |||||||
1. | Semen (1 zak=50 kg) | 185.00 | Zak | 90,000.00 | 16,650,000.00 | ||||
2. | Pasir beton | 29.00 | M3 | 160,000.00 | 4,640,000.00 | ||||
3. | Pasir urug | 4.00 | M3 | 140,000.00 | 560,000.00 | ||||
4. | Batu pecah uk. 2/3 | 3.00 | M3 | 400,000.00 | 1,200,000.00 | ||||
5. | Batu belah uk. 10/15 | 61.00 | M3 | 200,000.00 | 12,200,000.00 | ||||
6. | Papan mal uk. 2/18 cm-4m | 13.00 | Kpg | 24,000.00 | 312,000.00 | ||||
7. | Kayu 4/6- 4m | 13.00 | Btg | 20,000.00 | 260,000.00 | ||||
8. | Paku campur | 2.00 | Kg | 22,000.00 | 44,000.00 | ||||
9. | Kayu cerucuk D.10 cm- 4 m | 100.00 | Btg | 12,000.00 | 1,200,000.00 | ||||
Jumlah Bahan | 37,066,000.00 | ||||||||
II. | SEWA ALAT (sesuai keperluan) | ||||||||
1. | Gerobak Dorong | 2.00 | Bh | 200,000.00 | 400,000.00 | ||||
Jumlah Alat | 400,000.00 | ||||||||
III. | UPAH | ||||||||
1. | Pekerja | 101.00 | HOK | 85,000.00 | 8,585,000.00 | ||||
2. | Tukang | 40.00 | HOK | 120,000.00 | 4,800,000.00 | ||||
3. | Kepala Tukang | 4.00 | HOK | 140,000.00 | 560,000.00 | ||||
4. | Mandor | 8.00 | HOK | 120,000.00 | 960,000.00 | ||||
153.00 | HOK | Jumlah Upah | 14,905,000.00 | ||||||
IV. | HONOR TPK | ||||||||
1. | Ketua | 1.00 | org | 450,000.00 | 450,000.00 | ||||
2. | Sekretaris | 1.00 | org | 400,000.00 | 400,000.00 | ||||
3. | Anggota | 2.00 | org | 350,000.00 | 700,000.00 | ||||
(Perbup Sanggau No. 1 Thn. 2019) | |||||||||
4.00 | org | Jumlah Honor TPK | 1,550,000.00 | ||||||
J U M L A H (Rp.) | 53,921,000.00 |