RENCANA ANGGARAN BIAYA (RAB) | |||||||||
DESA PASIR BERDENGUNG KECAMATAN PASIR LAUT | |||||||||
TAHUN ANGGARAN 2020 | |||||||||
Bidang | : | Pelaksanaan Pembangunan Desa (2) | |||||||
Sub Bidang | : | Energi dan Sumber Daya Mineral (2.7.) | |||||||
Kegiatan | : | Pembangunan Sarana dan Prasarana Energi Alternatif Tingkat Desa (2.7.02.) | |||||||
Pembangunan Jaringan Listrik Tenaga Surya (PLTS) Dusun Bahagia - 48 unit | |||||||||
Waktu Pelaksanaan | : | 30 (tiga puluh hari kalender) | |||||||
Rincian Pendanaan | : | ||||||||
NO. | U R A I A N | VOLUME | HARGA SATUAN (Rp) | JUMLAH (Rp) | |||||
1 | 2 | 3 | 4 | 5 | |||||
I. | BAHAN | (harga utk contoh sj.) | |||||||
1. | Solar Modul Monocrystalline, kap. 60 Wp | 48.00 | unit | 1,700,000.00 | 81,600,000.00 | ||||
2. | Batteray control unit & Batteray box | 48.00 | unit | 1,150,000.00 | 55,200,000.00 | ||||
3. | Batteray VRLA | 48.00 | unit | 3,300,000.00 | 158,400,000.00 | ||||
4. | Kabel modul surya @ 7 m per unit | 336.00 | m | 18,000.00 | 6,048,000.00 | ||||
5. | Kabel instalasi @25 m per unit | 1,200.00 | m | 12,000.00 | 14,400,000.00 | ||||
6. | Lampu Led DC 12 volt 3 watt @3 bh | 144.00 | buah | 36,000.00 | 5,184,000.00 | ||||
7. | Kap lampu & perlengkapan | 48.00 | set | 60,000.00 | 2,880,000.00 | ||||
8. | Penyangga modul & tiang galvanis 3" | 48.00 | meter | 220,000.00 | 10,560,000.00 | ||||
9. | Stop kontak double | 96.00 | unit | 90,000.00 | 8,640,000.00 | ||||
10. | Tool kit | 48.00 | set | 90,000.00 | 4,320,000.00 | ||||
11. | Aksesoris | 48.00 | unit | 60,000.00 | 2,880,000.00 | ||||
Jumlah Bahan | 350,112,000.00 | ||||||||
II. | SEWA ALAT (sesuai keperluan) | ||||||||
Jumlah Alat | 0.00 | ||||||||
III. | UPAH | ||||||||
1. | Pekerja | 96.00 | HOK | 85,000.00 | 8,160,000.00 | ||||
2. | Tukang | 144.00 | HOK | 120,000.00 | 17,280,000.00 | ||||
3. | Kepala Tukang | 0.00 | HOK | 140,000.00 | 0.00 | ||||
4. | Mandor | 72.00 | HOK | 120,000.00 | 8,640,000.00 | ||||
312.00 | HOK | Jumlah Upah | 34,080,000.00 | ||||||
IV. | HONOR TPK | ||||||||
1. | Ketua | 1.00 | org | 450,000.00 | 450,000.00 | ||||
2. | Sekretaris | 1.00 | org | 400,000.00 | 400,000.00 | ||||
3. | Anggota | 3.00 | org | 350,000.00 | 1,050,000.00 | ||||
(Perbup Sanggau No. 1 Thn. 2019) | |||||||||
5.00 | org | Jumlah Honor TPK | 1,900,000.00 | ||||||
J U M L A H (Rp.) | 386,092,000.00 |