RENCANA ANGGARAN BIAYA (RAB) | |||||||||
DESA PASIR BERDENGUNG KECAMATAN PASIR LAUT | |||||||||
TAHUN ANGGARAN 2020 | |||||||||
Bidang | : | Pelaksanaan Pembangunan Desa (2) | |||||||
Sub Bidang | : | Pekerjaan Umum dan Penataan Ruang (2.3.) | |||||||
Kegiatan | : | Pembangunan Gapura (2.3.20.) | |||||||
Pembangunan Gapura RT. 1 RW. 2 Dusun Bahagia | |||||||||
Waktu Pelaksanaan | : | 10 (sepuluh hari kalender) | |||||||
Rincian Pendanaan | : | ||||||||
NO. | U R A I A N | VOLUME | HARGA SATUAN (Rp) | JUMLAH (Rp) | |||||
1 | 2 | 3 | 4 | 5 | |||||
I. | BAHAN | ||||||||
1. | Semen (1 zak=50 kg) | 22.00 | zak | 90,000.00 | 1,980,000.00 | ||||
2. | Pasir Beton | 3.00 | M3 | 125,000.00 | 375,000.00 | ||||
3. | Pasir Urug | 1.00 | M3 | 110,000.00 | 110,000.00 | ||||
4. | Batu 2/3 cm (kerikil) | 2.00 | M3 | 500,000.00 | 1,000,000.00 | ||||
5. | Besi beton polos dia. 8 mm-12 m | 36.00 | Btg | 50,000.00 | 1,800,000.00 | ||||
6. | Kawat Beton (Bendrat) | 3.00 | Kg | 25,000.00 | 75,000.00 | ||||
7. | Papan Mal uk. 2/18 cm- 4m | 8.00 | Kpg | 40,000.00 | 320,000.00 | ||||
8. | Kayu cerucuk untuk perancah | 10.00 | Btg | 7,000.00 | 70,000.00 | ||||
9. | Kayu 4/6 - 4m | 8.00 | Btg | 25,000.00 | 200,000.00 | ||||
10. | Paku Campur | 2.00 | Kg | 20,000.00 | 40,000.00 | ||||
11. | Plastik untuk Alas Cor Beton | 34.00 | M2 | 5,000.00 | 170,000.00 | ||||
12. | Batako uk. 7 x 15 x 30 cm | 275.00 | Bh | 3,000.00 | 825,000.00 | ||||
13. | Batu Alam Andesit 20x40 cm | 18.00 | M2 | 100,000.00 | 1,800,000.00 | ||||
14. | Cat Dasar | 2.00 | Liter | 50,000.00 | 100,000.00 | ||||
15. | Cat Kilat Dinding | 2.00 | Liter | 65,000.00 | 130,000.00 | ||||
16. | Amplas | 3.00 | Lbr | 5,000.00 | 15,000.00 | ||||
17. | Alat Bantu (Kuas) | 2.00 | Bh | 20,000.00 | 40,000.00 | ||||
Jumlah Bahan | 9,050,000.00 | ||||||||
II. | SEWA ALAT (sesuai keperluan) | ||||||||
1. | Gerobak Dorong | 1.00 | Bh | 200,000.00 | 200,000.00 | ||||
Jumlah Alat | 200,000.00 | ||||||||
III. | UPAH | ||||||||
1. | Pekerja | 40.00 | HOK | 85,000.00 | 3,400,000.00 | ||||
2. | Tukang | 19.00 | HOK | 120,000.00 | 2,280,000.00 | ||||
3. | Kepala Tukang | 2.00 | HOK | 140,000.00 | 280,000.00 | ||||
4. | Mandor | 3.00 | HOK | 120,000.00 | 360,000.00 | ||||
64.00 | HOK | Jumlah Upah | 6,320,000.00 | ||||||
IV. | HONOR TPK | ||||||||
1. | Ketua | 1.00 | org | 300,000.00 | 300,000.00 | ||||
2. | Sekretaris | 1.00 | org | 250,000.00 | 250,000.00 | ||||
3. | Anggota | 2.00 | org | 200,000.00 | 400,000.00 | ||||
(Perbup Sanggau No. 1 Thn. 2019) | |||||||||
4.00 | org | Jumlah Honor TPK | 950,000.00 | ||||||
J U M L A H (Rp.) | 16,520,000.00 | ||||||||
Pasir Bedengung, 31 Oktober 2019 | |||||||||
Disetujui : | |||||||||
Kepala Desa Pasir Bedengung | Kasi Kesejahteraan | ||||||||
Bunga Citra Lovestory, SH. | Ramlee |
BACA JUGA : Cara Menghitung Komposisi Campuran Beton Mutu K-175
BACA JUGA : Koefisien (Indeks) Bahan, Alat & Upah Pekerjaan Beton